Stage payments for an extension or renovation

By Alex Williams, director of Ty Parc Construction, a building contractor in Newport, South Wales · Last reviewed 21 October 2026

Pay a builder in stages as work is finished, not by date and not mostly upfront. A common pattern is a 10% deposit, then payments at foundations, walls and roof structure, roof and windows, first fix and second fix, with about 10% left until the job is finished and snagged. A deposit above 25% is a warning sign. Build your own schedule with the free tool below.

Build my payment schedule — free

A typical schedule

StageWhen it’s dueShare
DepositOn signing10%
FoundationsFoundations complete and signed off by building control15%
Walls and roof structureWalls to plate level and roof structure up20%
Roof and windowsRoof covered, windows in15%
First fixFirst fix plumbing and electrics, plastering15%
Second fixSecond fix and decoration15%
CompletionJob complete and snags fixed10%

One published UK example (Planning Signal, reviewed April 2026). Simple jobs need fewer stages; your contract should say what triggers each one.

How much deposit is fair?

10–15% is common. It covers booking your slot and early materials. Be wary of anything above 25%. For bespoke items ordered early, such as windows or a kitchen, a separate materials payment against an invoice is reasonable.

Holding money back until snagging

There are two common ways to do it:

  • Hold the final 10% until the snags are fixed.
  • Hold 5% of each payment, and release half at completion and half after a 6–12 month defects period.

Agree it in writing at the start. “Retention” is being banned in commercial construction contracts by the Commercial Payments Bill, but that’s aimed at business contracts — on a home job, an agreed holdback is still normal.

What triggers a payment

  • Define each stage by something you can see (“roof felted and battened”), not a date.
  • The builder asks for payment when a stage is done.
  • You check and pay within the agreed number of days.
  • If something’s not right, say what and pay the part that’s agreed.

Extras change the schedule

When an extra is agreed, agree when it’s paid — usually with the next stage. Keep a running total so the last payment isn’t a surprise. Credits for work taken out come off the total too. At the end, the final account brings it all together.

Builders: setting your schedule

Front-load only what covers materials you’ve genuinely committed to. Make every stage something the client can see, and send the schedule with the quote. Put it in a written contract — see JCT, FMB and simple building contracts — and if a stage payment goes unpaid, see the letter before action guide.